Personal story / Moscow Region / 2023–2026

Uglovoy
Kvartal.

Three adjoining plots in Klin made it possible to build in phases. The barn-style and modular homes show how construction choices tie in with the guest experience and day-to-day operations.

Barn-style home with a tall glazed gable beside a green slope
Barn-style home in June 2025. The glazed gable opens the house to the terrace, and the side faces a green slope.
By entrepreneur Stanislav BatychkoScope: construction and rentalsPeriod: 2023–2026
01From strategy to site

Why I chose three adjoining plots

In summer 2023 I reviewed plots offered at land auctions in the Moscow Region. I compared locations on maps first and visited the sites after bidding. Three adjoining plots in Klin let me concentrate the work in one place and open the homes in phases.

I was still selling land near Krasnodar. As proceeds came in, I put part of them into construction. The renovations on Sobornaya and Mira had taught me to evaluate a future home as the person who would be responsible for it after the keys were handed over.

After selling an urban property, I looked for another opportunity where my decisions could add value. That was the appeal of rural land. The result depended on choosing the plot, building the house, connecting utilities and how comfortable the finished home would be to live in.

Steel perimeter frame on supports above the grass
October 2023. The supports and perimeter frame are in place. The footprint of the future house is already visible.

My role

From land selection to the first guest

I chose the plots and house formats, signed contracts and scheduled payments. On site I coordinated the contractors’ work with water and drainage installation. After construction I handled the fit-out and organised rentals.

02Construction in practice

First contract in August, two more in autumn

Before starting, I compared country-rental formats. I created a table covering home size, use of the grounds and guest services. I started with a small house. In late August 2023 I signed with Tekhnologiya, and by December the home was registered.

I signed contracts for the next two homes in September and October. Construction continued in 2024. My records indicate that both were registered in the spring. Registration was one step; utilities, furniture and the grounds still had to be ready for the first check-in.

First house: assembling a wall outdoors
November 2023. Studs and bracing have been assembled into walls. The base is still visible beneath the frame.
Two builders installing a roofing sheet on a pitched roof
February 2024. One worker passes a profiled sheet up from a ladder, and the other receives it on the roof.
03Grounds and infrastructure

Water, access and responsibilities

While builders put up the homes, I organised water supply and drainage. I worked with local officials and specialist organisations on roads, electricity, gas and connectivity. For each task I had to clarify who was responsible for that stretch of infrastructure and when the next work could begin.

In 2024 the plots went from leased to owned. As I recall, I signed the first purchase contract in January and the other two in May.

Drilling tool by a winter excavation.
Drilling tool by a winter excavation.
Scaffold work on the facade with tall glazing
February 2024. Window openings at both levels are visible on the gable. Working around the upper windows requires scaffolding.
Home, landscaped grounds and outdoor leisure area: site development after construction.
Home, landscaped grounds and outdoor leisure area: site development after construction.
Sunny timber terrace at the modular home in autumn
The modular home in autumn 2024. The roof extends over the timber terrace.
Dining and living areas of the barn-style house, seen from the upper level
Inside the barn-style house. The staircase, dining area and living room are visible from the upper level.
04The finished offer

The houses begin welcoming guests

After construction I handled furnishing, landscaping and maintenance. We added outdoor soaking tubs. Guests need a kitchen and dining area indoors, and easy access and a place to relax outside. All became part of day-to-day operations.

In 2025 I focused on rentals and upkeep. In my experience, rates and occupancy were higher here than at my earlier projects in southern Russia.

The tall gable created room for an upper level in the barn-style home. The kitchen and living area share an open space downstairs. In the modular home, the covered terrace extends everyday living outside. On the same grounds, the two homes offer different ways to spend a few days away.

Ask the owner about available dates

Call about bookings

Illuminated modular home at dusk
The modular home in the evening. The broad glazing opens a view of the grounds from the living room.
Wood-heated outdoor soaking tub, part of the leisure amenities.
Wood-heated outdoor soaking tub, part of the leisure amenities.
05Lessons and the next cycle

What changed after the first season

With construction finished, guest operations continued. My records show work began on three bathhouses in Klin in 2026.

For subsequent plots I recalculated the cost of entry. I also toured container-home production to examine structures and service layouts. It remained a feasibility study for a potential pilot.

Exploring container technology at the factory: a separate study, not a completed Uglovoy Kvartal property.
Exploring container technology at the factory: a separate study, not a completed Uglovoy Kvartal property.